Department of Water Resources, RD & GR
PROGRESS AFTER INCLUSION IN PMKSY (from 01/04/2016)
OVERALL PROGRESS
Status as on 19/04/24
Completed Projects
49.15%
No. of Projects : 118
No. of Completed Projects : 58
Irrigation Potential Created
67.95%
Target Irrigation Potential (in Hectare) : 3989.61
Irrigation Potential Created (in Hectare) : 2711.02
Central Assistance
58.06%
Target Central Assistance (in Rs.) : 28866
Central Assistance Released (in Rs.) : 16761
Total Expenditure
77.32%
Estimated Cost (in Rs.) : 94619
Total Expenditure (in Rs.) : 73162
Target vs Completed Projects
IPC
Central Assistance
Expenditure