PROGRESS AFTER INCLUSION IN PMKSY (from 01/04/2016)
OVERALL PROGRESS
Status as on 21/08/25
Completed Projects
54.47%
No. of Projects : 123
No. of Completed Projects : 67
Irrigation Potential Created
61.62%
Target Irrigation Potential (in Hectare) : 4538.57
Irrigation Potential Created (in Hectare) : 2796.70
Central Assistance
56.01%
Target Central Assistance (in Rs.) : 59138
Central Assistance Released (in Rs.) : 33126
Total Expenditure
66.58%
Estimated Cost (in Rs.) : 152505
Total Expenditure (in Rs.) : 101538
Target vs Completed Projects
IPC
Central Assistance
Expenditure