Department of Water Resources, RD & GR
PROGRESS AFTER INCLUSION IN PMKSY (from 01/04/2016)
OVERALL PROGRESS
Status as on 31/08/23
Completed Projects
45.30%
No. of Projects : 117
No. of Completed Projects : 53
Irrigation Potential Created
64.55%
Target Irrigation Potential (in Hectare) : 3517.86
Irrigation Potential Created (in Hectare) : 2270.65
Central Assistance
90.36%
Target Central Assistance (in Rs.) : 18321
Central Assistance Released (in Rs.) : 16555
Total Expenditure
78.89%
Estimated Cost (in Rs.) : 91113
Total Expenditure (in Rs.) : 71880